Milestones
| Date | Contents | Notes |
|---|---|---|
| Dec. 13, 2024 | Phase 3 Space Planning Team – 1st Meeting | Space Planning Team (SPT) |
| Dec. 27, 2024 | Phase 3 Space Planning Team – 2nd Meeting | |
| Jan. 16, 2025 | Phase 3 Space Planning Team – 3rd Meeting | |
| Feb. 23, 2025 | College of Planning and Design – Design Thinking II: Student Presentations on Library Space Renovation Proposals | Incorporating into the curriculum (POV: students) |
| Mar. 3, 2025 | Phase 3 Space Planning Team – 4th Meeting | |
| Mar. 17, 2025 | Site Visit – NTU Library & National Central Library | taking experiences from peer units as a reference |
| Mar. 19, 2025 | Phase 3 Space Planning Team – 5th Meeting | |
| Mar. 26, 2025 | Phase 3 Space Planning Team – 6th Meeting | planning scope adjusted due to the exterior wall waterproofing issue |
| Apr. 14–15, 2025 | 1F Lobby, East Side · New Furniture Installed | 1F Lobby, East Side – Setup completed |
| May 2, 2025 |
|
|
| June 24, 2025 | Vendor Service Proposal, initial review by SPT | initial review as a reference for committee |
| June 26, 2025 | Procurement Evaluation Committee Meeting | winning vendor confirmed |
| June 27, 2025 | Phase 3 Space Planning Team – discussion Meeting | Discussion on feedback committee |
| July 9, 2025 | Phase 3 Space Renovation Project – Schematic Design Review 1st Meeting | Pre-Meeting on Schematic Design by SPT |
| July 16, 2025 | Phase 3 Space Renovation Project – Schematic Design Review 2nd Meeting | Pre-Meeting on Schematic Design by SPT |
| July 24, 2025 | Main Library Phase 3 Creative Furniture Design & Procurement Project – Schematic Design Review 1st Meeting | Review of designs by committee (confirmed) |
| Aug. 4, 2025 | Main Library Phase 3 Creative Furniture Design & Procurement Project – Schematic Design Review 2nd Meeting |
|
| Aug. 15, 2025 | Phase 3 Space Planning Team – 8th Meeting | Pre-Meeting on Detailed Design by SPT |
| Aug. 27, 2025 | Main Library Phase 3 Creative Furniture Design & Procurement Project – Detailed Design Review 1st Meeting | Review of designs by committee |
| Sep. 8, 2025 | Main Library Phase 3 Creative Furniture Design & Procurement Project – Detailed Design Review 2nd Meeting |
|
| Sep. 17, 2025 | Phase 3 Space Planning Team – discussion Meeting. | Pre-meeting of Pre-Construction Coordination Meeting |
| Sep. 26, 2025 | Pre-Construction Coordination Meeting. | coordinate construction access routes, inter-section coordination, and site supervisor shift schedule. |
| Sep. 30, 2025 | Groundbreaking Ceremony. | |
| Oct. 1, 2025 | Construction Start Date. | |
| Oct. 8, 2025 | 1st Construction Meeting. | confirmation of three-week rolling schedule, construction crew access routes, coordination of work precautions. |
| Oct. 15, 2025 | 2nd Construction Meeting. | |
| Oct. 22, 2025 | 3rd Construction Meeting. | Proposal for 2nd alteration of design. (5F study carrels) |
| Oct. 29, 2025 | 4th Construction Meeting. | Discussion on access contral plan of study carrels. |
| Nov. 6, 2025 | 5th Construction Meeting. | Discussion on the Setup of the 1F Soundproof Booth. |
| Nov. 19, 2025 | 6th Construction Meeting. | Discussion on setup of Donation Wall, and placement of Soundproof Booth on 5F. (Note: Work suspended on 11/12 due to a typhoon) |
| Nov. 26, 2025 | 7th Construction Meeting. |
|
| Dec. 3, 2025 | 8th Construction Meeting. |
|
| Dec. 5, 2025 | The contractor submit the project completion report. | |
| Dec. 9, 2025 | Inspection by Space Planning Team. | Inspection and acceptance (numbers, functions, specs) |
| Dec. 11, 2025 | Inspection by Library (operation-related) | Inspection and acceptance (numbers, functions, specs) |
| Dec. 16, 2025 | Inspection by Purchasing Division | Inspection and acceptance (numbers, functions, specs) |
| Dec. 23, 2025 | Opening Event | Opening & Tours.
|