Milestones
Date | Contents |
---|---|
Mar. 2014 | NCKU Library established Space Planning Team. |
Apr. 2017 | The “KnowLEDGE” learning commons was officially put to normal use. |
Jul. 2017 | All the librarians attended the Library Space Renovation Workshop. |
Aug. 2018~Jul. 2019 | Professional design company was commissioned to propose plans for early-stage library space renovation plan. |
Oct. 19, 2018~Jan. 11, 2019 | NCKU held the interactive exhibition of “One Hundred Possible Dreams for NCKU Library” and, there were students from various college/department participating in the “Workshop for Dreamed NCKU Library”. |
Jun. 2019~Apr. 2020 | Meeting for discussing the preparation related to the Phase I Space Renovation Work was held. |
Apr. 2020 ~ Jul. 28, 2020 | NCKU officially activated the Phase I Space Renovation Work and bidding process and held relevant meetings. |
Jul. 17, 2020~Aug. 10, 2020 | The library conducted internal discussion meeting and the conveyed a meeting discussing design modification with the winning tenderer. |
Aug. 17, 2020 | First review meeting for the basic design of the Library 1st Floor Space Renovation was held. |
Aug. 21, 2020 | The library conveyed the meeting discussing design modification with the winning tenderer after the first review meeting for the basic design |
Aug. 25, 2020 | Second review meeting for the basic design of the Library 1st Floor Space Renovation was held and the designed was approved. |
2Sep. 3, 2020~Sep. 16, 2020 | After the basic design review was approved, the Library conveyed a meeting discussing the detailed design modification with the winning tenderer. |
Sep. 24, 2020 | First review meeting for the detailed design of Library 1st floor space was held and the design was approved. |
Sep. 30, 2020 | Second written review meeting for the detailed design of Library 1st floor space was held and the design was approved. |
Oct. 3, 2020 | NCKU issued the news about “announcement for adjustment to some services due to the construction of library space renovation project”. |
Oct. 6, 2020 | Coordination meeting before the construction of 1st floor space renovation & 1st Work Meeting was held |
Oct. 8, 2020 | The renovation was officially started by entering the site to remove the counter, carpet, and furniture. |
Oct. 10, 2020 | Demolition work was completed, and the dust prevention and separation measures were completed. |
Oct. 13, 2020 |
|
Oct. 20, 2020 | 3rd Work Meeting for 1st floor space renovation was held. |
Oct. 22, 2020 | Carpentry and renovation technicians joined the project. The position and sizes of I DESK, E HUB, and S Service confirmed. |
Oct. 28, 2020 | Relocation of control box connected to the fire roller shutters was completed. |
Oct. 29, 2020 |
|
Oct. 29, 2020 | The position of turnstile gate and I DESK workstation had been confirmed. |
Oct. 31, 2020 |
|
Nov. 2, 2020 | Testing of fire roller shutters sensor has been done. |
Nov. 3, 2020 | 5th Work Meeting for 1st floor space renovation was held. |
Nov. 7, 2020 | Cable routing through ceilings commenced. |
Nov. 10, 2020 | 6th Work Meeting for 1st floor space renovation was held. |
Nov. 13,2020 | Woodworking projects for I DESK, E HUB, S Service, New Arrivals were completed. |
Nov. 19, 2020 |
|
Nov. 24, 2020 |
|
Nov. 25, 2020 |
|
Dec. 14, 2020 | NCKU Main Library Brand-New 1st Floor to Reopen at 11 am, December 16, 2020. |