Milestones
Date Contents
Mar. 2014 NCKU Library established Space Planning Team.
Apr. 2017 The “KnowLEDGE” learning commons was officially put to normal use.
Jul. 2017 All the librarians attended the Library Space Renovation Workshop.
Aug. 2018~Jul. 2019 Professional design company was commissioned to propose plans for early-stage library space renovation plan.
Oct. 19, 2018~Jan. 11, 2019 NCKU held the interactive exhibition of “One Hundred Possible Dreams for NCKU Library” and, there were students from various college/department participating in the “Workshop for Dreamed NCKU Library”.
Jun. 2019~Apr. 2020 Meeting for discussing the preparation related to the Phase I Space Renovation Work was held.
Apr. 2020 ~ Jul. 28, 2020 NCKU officially activated the Phase I Space Renovation Work and bidding process and held relevant meetings.
Jul. 17, 2020~Aug. 10, 2020 The library conducted internal discussion meeting and the conveyed a meeting discussing design modification with the winning tenderer.
Aug. 17, 2020 First review meeting for the basic design of the Library 1st Floor Space Renovation was held.
Aug. 21, 2020 The library conveyed the meeting discussing design modification with the winning tenderer after the first review meeting for the basic design
Aug. 25, 2020 Second review meeting for the basic design of the Library 1st Floor Space Renovation was held and the designed was approved.
2Sep. 3, 2020~Sep. 16, 2020 After the basic design review was approved, the Library conveyed a meeting discussing the detailed design modification with the winning tenderer.
Sep. 24, 2020 First review meeting for the detailed design of Library 1st floor space was held and the design was approved.
Sep. 30, 2020 Second written review meeting for the detailed design of Library 1st floor space was held and the design was approved.
Oct. 3, 2020 NCKU issued the news about “announcement for adjustment to some services due to the construction of library space renovation project”.
Oct. 6, 2020 Coordination meeting before the construction of 1st floor space renovation & 1st Work Meeting was held
Oct. 8, 2020 The renovation was officially started by entering the site to remove the counter, carpet, and furniture.
Oct. 10, 2020 Demolition work was completed, and the dust prevention and separation measures were completed.
Oct. 13, 2020
  • 2nd Work Meeting for 1st floor space renovation was held.
  • Power supply, network, and phone lines setting out and line check work were completed.
Oct. 20, 2020 3rd Work Meeting for 1st floor space renovation was held.
Oct. 22, 2020 Carpentry and renovation technicians joined the project. The position and sizes of I DESK, E HUB, and S Service confirmed.
Oct. 28, 2020 Relocation of control box connected to the fire roller shutters was completed.
Oct. 29, 2020
  • 4th Work Meeting for 1st floor space renovation was held.
  • Parts of the recessed downlight have been replaced.
Oct. 29, 2020 The position of turnstile gate and I DESK workstation had been confirmed.
Oct. 31, 2020
  • Electrical wiring installation and other detailed works in carpentry area were completed.
  • Cable routings area on B1 confirmed.
Nov. 2, 2020 Testing of fire roller shutters sensor has been done.
Nov. 3, 2020 5th Work Meeting for 1st floor space renovation was held.
Nov. 7, 2020 Cable routing through ceilings commenced.
Nov. 10, 2020 6th Work Meeting for 1st floor space renovation was held.
Nov. 13,2020 Woodworking projects for I DESK, E HUB, S Service, New Arrivals were completed.
Nov. 19, 2020
  • 7th Work Meeting for 1st floor space renovation was held.
  • Projects for painting and molding exposed concrete were completed.
Nov. 24, 2020
  • 8th Work Meeting for 1st floor space renovation was held.
  • Carpet Installation Complete.
Nov. 25, 2020
  • Installation of system furniture was completed.
  • Arrival and construction of flower-shaped tables, chairs, under-desk computer holder, and end tables.
Dec. 14, 2020 NCKU Main Library Brand-New 1st Floor to Reopen at 11 am, December 16, 2020.